Slip Ring Rebuild
A customer called overnight because they had a slip ring failure on one of two synchronous motors and that halted production. Horner was on site in the morning to assess the situation and it was determined that an on site repair was not feasible. The unit was disassembled and transported to the Terre Haute shop for rebuild.
By securing customer supplied brushes, brushholders (which are now obsolete), Horner stock to fabricate insulators and with the help of Horner Machining Services, we were able to have the unit back on site within just a few days. Horner was onsite for the eight hour re-assembly, providing techincal support to the customer maintenance team. We are proud to support customers repair needs every step of the way.


Other Posts
Chiller 1000HP Soft Starter
An ethanol facility that processes corn into fuel recently upgraded a critical chiller application with the installation of a 1000 HP, 4160V Benshaw medium-voltage soft starter. What began as a transformer repair discussion ultimately evolved into a full system improvement [...]
Combine Vibration Troubleshooting
Horner Field Service was recently asked to troubleshoot a vibration issue with a combine. The call came in to Ralph Coonce on a Thursday afternoon. It didn’t take long for Ralph to determine that he was going to send me. [...]
Rubber Plant Motor Failure
A 400HP WEG motor on the hydraulic power unit of a plant’s main mixer failed due to a catastrophic drive-end (DE) bearing issue. The bearing failure generated sparks and halted the production of raw rubber critical for automotive products. With [...]